Sunday, November 03, 2024 Farm Update

let’s start with our sawmill structures trials and tribulations.

main home construction — highlights

looking into our underground water tank
Our construction manager pumped out and wiped down the floor of our cistern. That’s good.

This week, we may accomplish the following tasks on the construction site:

  • Plumber Tim Mayne returns. Sewer system connection. Water filtration and sterilization.
  • Bulk water delivery into the above pictured cistern. And properly seal the hatch.
  • Charge up and condition the infloor heating fluid system.
  • Test burn the boiler.
  • Bunkie roofing gets delivered. TS, SB and PN cap off the bunkie before the constant rain (or sleet and snow) descends upon us.
  • The painters show up and finish their interior work.
  • Electricians.